Journal of Construction Engineering and Management · 2005 · 136 citations · 12 references
ManagementConstruction ManagementProject ManagementConstruction EngineeringConstruction Project ManagementCost ManagementBuilding PerformanceBuilding Performance AssessmentConstruction PlanningCost EstimationProject Cost ManagementTime-cost Tradeoff AnalysisConstruction Cost ForecastingCost PerformanceCost-performance ModelingMultiple RegressionProject Duration PredictionProject Scope AnalysisProject Time PerformanceWeighted Least Squares
The study proposes an alternative model to Bromilow’s 1980s approach for forecasting time and cost performance in construction projects. Using weighted least squares multiple regression on 161 Australian construction projects, the authors examined how project duration, type, procurement method, tender type, gross floor area, and number of stories predict time performance, and proposed an alternative forecasting model. The analysis found that gross floor area and building height are the main determinants of project duration, while cost is a weak predictor, and the authors discuss limitations and practical implications.
Project time–cost relationships were examined by using project scope factors as predictors for 161 construction projects that were completed in various Australian States using the multiple regression technique of weighted least squares. The analysis was performed between project duration (i.e., time), project type, procurement method, tender type, gross floor area (GFA), and number of stories. An alternative model to that proposed by Bromilow more than three decades ago for forecasting time and cost performance is proposed. It is shown that GFA and the number of stories in a building are key determinants of time performance in projects. Furthermore, the results indicate that cost is a poor predictor of time performance. Limitations and practical implications of the research are also presented.
12