Operations Research · 2004 · 134 citations · 44 references
ManagementProject ManagementNew Product DevelopmentProduction PlanningSchedulingConcurrent EngineeringProduct DevelopmentProduct Life Cycle ManagementProduct PlanningTime-cost Tradeoff AnalysisConcurrent Product DevelopmentCrashing With Resource ConstraintsIntegrated Product DevelopmentOptimal PoliciesProduct Development ProcessProject Overlap ManagementSchedule Crashing
This research addresses two common tools for reducing product development lead times: overlapping of development stages and crashing of development times. For the first time in the product development literature, a formal model addresses both tools concurrently, thus facilitating analysis of the interdependencies between overlapping and crashing. The results exhibit the necessity of addressing overlapping and crashing concurrently, and exhibit general characteristics of optimal overlapping/crashing policies. The impact of different evolution/sensitivity constellations on optimal policies is investigated, and comprehensive guidelines for structuring development processes are provided. For the special case of linear costs, an efficient procedure is presented that generates the efficient time-cost trade-off curves and determines the corresponding optimal overlapping/crashing policies. The impact of key parameters and the robustness regarding their estimates is illustrated with a simple two-stage example.
44
The new new product development game
Journal of Product Innovation Management · 1986 · 1.6K citations
Developing products in half the time
Choice Reviews Online · 1991 · 942 citations
Management, Manufacturing Engineering, New Product Development +7
Software project dynamics: an integrated approach
Choice Reviews Online · 1991 · 674 citations
Management, Human Resource Management, Project Management +16