Causes of delay in road construction projects in Malawi

Moses Kamanga, Wynand JvdM Steyn

UpSpace Institutional Repository (University of Pretoria) · 2013 · 56 citations · 13 references

Full text

Open access

Concepts

Abstract

A study was conducted to identify the causes of delay in completing road construction
\nprojects in Malawi. A literature review was done which yielded 72 typical causes of delay, and
\na questionnaire was sent to client, contractor and consultant representatives in Malawi. The
\nresults were analysed using the Relative Importance Index (RII) and Spearman’s Rank Correlation
\nCoefficients, which indicated that the top ten causes of delay in Malawi are: shortage of fuel,
\ninsufficient contractor cash-flow, shortage of foreign currency for importation of materials and
\nequipment, slow payment procedures adopted by the client in making progress payments,
\ninsufficient equipment, delay in relocating utilities, shortage of construction materials, delay
\nin paying compensation to land owners, shortage of technical personnel, and delay in site
\nmobilisation. The causes of delay are significant and should be given attention by client
\norganisations, consultants and contractors to enable the timely completion of projects in
\nfuture. It should also be noted that most of the causes of delay are not unique to Malawi, and
\nhave been observed in other southern African countries such as South Africa, Botswana and
\nSwaziland. Recommendations are made to prevent similar causes of delay in future.