Responding to schedule changes in build‐to‐order supply chains

Lee J. Krajewski, Jerry C. Wei, Ling-Lang Tang

Journal of Operations Management · 2004 · 182 citations · 40 references

DOIFull text

Open access

Concepts

TL;DR

In build‑to‑order supply chains, suppliers adopt either a “reduce uncertainty” strategy with restrictive contracts and infrequent revisions or a “cope with uncertainty” strategy with flexible contracts and frequent revisions. This multiple case study investigates how suppliers react to short‑term schedule changes in build‑to‑order supply chains and proposes eight propositions linking supplier power, process flexibility, and reaction strategy. The authors analyze the supply‑chain processes linking a notebook computer manufacturer with five component suppliers. The study identifies two distinct reaction strategies among the five buyer‑supplier dyads and suggests directions for future research.

Abstract

Abstract This multiple case study explores the reaction strategies suppliers use to respond to short‐term dynamics of schedule changes in build‐to‐order supply chains. We examine the relationship and supply chain processes between a notebook computer manufacturer and five component suppliers. Two distinct reaction strategies emerge from these five buyer–supplier dyads. The “reduce uncertainty” strategy emphasizes supply contracts with a high degree of restrictiveness, relatively infrequent schedule revisions, and a high level of form postponement. The “cope with uncertainty” strategy emphasizes flexible supply contracts, relatively frequent schedule revisions, and low levels of form postponement. Eight propositions are formulated to understand the linkage between a supplier's power, its short‐term process flexibility, and the elements of its reaction strategy. The paper concludes by proposing future research directions.

References

40