2012 · 10 citations · 0 references
EngineeringCivil EngineeringEarth SciencesErosion ControlGeotechnical EngineeringSediment TransportCheck DamsDebris ManagementErosionErosion ProcessesFlood Control EngineeringSediment ErosionDebris Flow DynamicsDebris FlowsDebris-laden Flood FlowsFlow HydraulicsHydraulic AnalysisHydraulic JumpsSediment-bed ResistanceStep-pool Structures
Experiments were conducted with an artificial step-pool system on the new Wenjiagou Gully to mitigate large volume debris flows in 2009.The step-pool system dissipated flow energy in steps and hydraulic jumps.Analysis proved that the step-pool system dissipated 2/3 of the kinetic energy of flow,thus the critical discharge for triggering debris flow increased threefold.Due to the step-pool system maximized the flow resistance and protected the bed sediment and banks from erosion,the rainstorm floods in 2009 did not trigger debris flows.In 2010 the step-pool system was replaced with 20 check dams.Huge boulders were broken into small pieces of diameter less than 0.5m and were used as building materials for the 20 dams.Without the protection of the step-pool system,a rainstorm flood scoured the base of the dams and caused the failure of check dams in Aug.2010.The flow incised the gully bed by 50m.The loose bank materials slid into the flow mixed with water and formed a large volume debris flow with a volume of 4.5 million m3.Many houses were buried by the debris flow and 12 people were killed.Comparison of the two strategies proved that energy dissipation structures are necessary for controlling large volume debris flows.Check dams,if they are stable,may reduce the potential of bank failures and control debris flows.The step-pool system dissipates flow energy and control gully bed incision and bank failure.A combination of check dams and step-pool systems may be the most effective for mitigating debris flows.