Scheduling the operations of a double-load crane in slab yards

Guodong Zhao, Jiyin Liu, Yun Dong

International Journal of Production Research · 2019 · 13 citations · 23 references

DOIFull text

Open access

Concepts

Abstract

This paper studies a double-load crane scheduling problem (DLCSP) in steel slab yards. A slab yard stores slabs in stacks. To prepare for use in production, some slabs need to be moved from one place to another. These movement tasks are performed by a double-load crane which can hold up to two slabs simultaneously. Given a set of tasks and possibly precedence relationships among them, the scheduling problem is to allocate the tasks to double-load operations and determine the schedule for the crane to perform the tasks so as to minimise the makespan. The problem is first formulated as a mixed integer linear programming (MILP) model with variables representing the order of tasks. Based on properties of the problem, it is then reformulated from a crane operation perspective. Computational experiments are carried out on practical data collected from a steel company. The results show that both models can solve practical sized problems optimally, with the second model being more efficient.

References

23