RAIRO - Operations Research · 2019 · 21 citations · 46 references
ManagementIndustrial EngineeringOperations ManagementInventory ControlInventory ManagementProduction PlanningInventory Cost AnalysisInventory OptimizationInventory TheoryLead Time AnalysisLead Time ManagementStochastic Inventory ModelsInventory Models With Lead TimesInventory Models With ShortagesLead Time OptimizationNet Present ValueReplenishmentReplenishment Lead TimeStochastic Lead TimeStochastic Lead-time Models
The paper studies an integrated vendor–buyer model with shortages under stochastic lead time which is assumed to be variable but depends on the buyer’s order size and the vendor’s production rate. The replenishment lead time and the market demand uncertainty are assumed to be reduced by changing the regular production rate of the vendor at the risk of paying additional cost. Shortages are partially backlogged and the backlogging rate depends on the length of the buyer’s replenishment lead time. The proposed model is formulated to obtain the net present value (NPV) of the expected total cost of the integrated system through optimization of (i) the buyer’s order quantity, (2) the buyer’s safety factor, and (3) the vendor’s production rate. Theoretical results are derived to demonstrate the existence and uniqueness of the optimal solution. Through extensive numerical study, some valuable managerial insights are obtained.
46