Pile-supported embankment over soft soil for a high-speed line

Laurent Briançon, Bruno Simon

Geosynthetics International · 2017 · 58 citations · 0 references

Concepts

TL;DR

In the new South Europe Atlantic high‑speed line, many embankments are built on very soft soil, including a high embankment on peat and clay for the Dordogne River bridge. The study aimed to minimize expected settlement and reduce construction time by designing a pile‑supported embankment (PE) and later proposing a geogrid‑reinforced piled embankment (GRPE) as an alternative. A full‑scale experimental embankment was constructed, using driven precast concrete piles with square heads for the PE design and a geogrid‑reinforced piled embankment (GRPE) to evaluate and compare settlement and stability. Measurements show that the GRPE system exhibits less settlement and greater stability than the PE solution, transferring load to the piles and limiting maximum geogrid strain to the ends and around pile heads.

Abstract

In the construction of the new South Europe Atlantic high-speed line, many embankments have been built on very soft soil. In particular, to access the new bridge constructed above the Dordogne River, a high embankment has been constructed on peat and clay. To minimise the expected settlement and to reduce construction time, a pile-supported embankment (PE) was initially designed based on driven precast concrete piles with a square pile head. A geogrid reinforced piled embankment (GRPE) system was proposed as a ground improvement method to replace the initial choice. To compare the efficiency of the GRPE system and the PE system, a full-scale experimental reinforced embankment was established. The measurements show that the GRPE system shows less settlement and is more stable than the PE solution, and therefore performs at least as well as the PE solution: the settlement is reduced and stabilised, the load is transferred to the piles and the maximum geogrid strain occurs at the end and around the pile heads in the lower geogrid.