International Journal of Mining Reclamation and Environment · 2017 · 18 citations · 13 references
EngineeringGeological EngineeringMining EngineeringGeotechnical EngineeringMine PlanningMine SafetyGeotechnical DesignOpen-pit Mine DesignGeomechanical DesignMine Planning IntegrationNet Present ValueNet Present Value EstimationOpen Pit Slope DesignOpen-pit Slope StabilityPit Design
The objective of this study is to integrate the admissible factor of safety (FoS) into the mine planning. The analysis showed, as expected, that a lower net present value (NPV) is obtained with the increase in the admissible FoS. Most importantly, it demonstrated that the FoS of the slopes of the adjacent phases, which are not part of the final pit, are considerably greater than the admissible FoS. Therefore, the NPV of an open pit mine project can be increased by steepening the slopes of adjacent phases that are not part of the final pit walls.
13
HOEK-BROWN FAILURE CRITERION - 2002 EDITION
E. Hoek, C. Carranza‐Torres, Brent Corkum · 2002 · 1.4K citations
Strength of jointed rock masses
E. Hoek · Géotechnique · 1983 · 747 citations
The Hoek–Brown Failure Criterion
Erik Eberhardt · Rock Mechanics and Rock Engineering · 2012 · 445 citations · Full text
Engineering, Industrial Engineering, Stochastic Processes +8