Meitan xuebao · 2008 · 10 citations · 0 references
EngineeringEarth SciencesMining EngineeringGeotechnical EngineeringMine ReclamationSoil MechanicsLand SubsidenceMine Land ReclamationSubsidence ManagementSubsidence MitigationMining-induced SubsidenceProper TimeReclamationSoil ReclamationSubsidenceSubsidence ControlSubsidence PredictionTime-dependent Subsidence Analysis
The proper time model of pre-reclamation was built using probability integration model and influence factors such as exploitation method,under water level and thickness of peeling off surface soil,etc..Through the experiment result,the counting result is T(Reclamation time)≤47 d.Compared with subsidence situation of surface points on the chief profile after 44 d of the mining and on the reference of the seasons elements,the reclamation action could get started after 47 d since the mining to meet the demand of the project.