Optimal Black Start Resource Allocation

Feng Qiu, Jianhui Wang, Chen Chen, Jianzhong Tong

IEEE Transactions on Power Systems · 2015 · 76 citations · 1 references

Concepts

Abstract

The restoration of the bulk power system after a partial or complete blackout relies on black-start (BS) resources. To prepare for system restoration, it is important to procure the right amount of BS resources at the right locations in the grid so that the total restoration time can be minimized. Achieving this goal requires that resource procurement planning takes the restoration process into account. In this study, we integrate the BS resource procurement decision with a restoration planning model and develop an optimization model that produces a minimal cost procurement plan that satisfies the restoration time requirement.

References

1