Installation and Testing Results of Long Island Transmission Level HTS Cable

80

Citations

5

References

2009

Year

Abstract

The first long length, transmission level voltage, cold dielectric, high temperature superconductor power cable has been successfully installed in the Long Island Power Authority (LIPA) grid. The cable is capable of carrying 574 MVA at a voltage of 138 KV. Three 600 m long phase conductors were manufactured and shipped to the LIPA site. The installation process included pulling three cables through three separate 600 m long underground conduits and assembly of three terminations at each end. The project has been funded by the US Department of Energy and is led by American Superconductor. The project team is comprised of Nexans, Air Liquide and LIPA. This paper describes the cable system, installation process and an overview of various testing results before and after installation. In addition, details of an initial successful cool-down process are presented. It also includes the performance results in grid operation.

References

YearCitations

Page 1