Journal of the Operations Research Society of Japan · 1986 · 82 citations · 10 references
ManagementIndustrial EngineeringOperations ManagementOperations PlanningProduction PlanningSchedulingCombinatorial OptimizationFlow Shop SchedulingJob SchedulingJob Shop SchedulingMachine SchedulingScheduling TheoryApproximate OptimizationFlow ShopScheduling With Sequence-dependent Setup TimesSequence-dependent Setup TimesSetup TimesStorage Space OptimizationStorage Space UtilizationTraveling Salesman Problem
The flowshop scheduling problem with sequence dependent setup times is considered and shown to be NP-complete. A traveling salesman problem formulation is proposed for the case where jobs are processed continuously through the shop. These results are used to describe an approximate algorithm for the case where limited or infinite intermediate storage space is available to hold partially completed jobs. The effectiveness of the proposed approximate approach is discussed and some empirical results are reported.