Design and Experimental Testing of a 1.9MWth Calcium Looping Pilot Plant

Ming‐Hui Chang, Weicheng Chen, Chin-Ming Huang, Wan‐Hsia Liu, Yiang‐Chen Chou, Wen-Chen Chang, Wang Chen, Jui-Yen Cheng, Kuo-En Huang, Heng‐Wen Hsu

Energy Procedia · 2014 · 125 citations · 7 references

DOIFull text

Open access

Concepts

Abstract

Calcium looping (CaL) CO 2 capture process using calcium oxide as a regenerable solid sorbent has been under development at the Industrial Technology Research Institute (ITRI) of Taiwan for several years. At 2013, the 1.9MW th pilot plant has been fully constructed, and the trial runs have been progressed for almost one year. The CO 2 was captured by CaO from the flue gas of the cement plant in a bubbling fluidized-bed carbonator while diesel oil oxy-combustion in the rotary kiln provides the heat required to regenerate the sorbent. The start-up progress of carbonator does not use pre-heating system, but take advantage of heat dissipated by the hot sorbent form the calciner. The flow rate of the flue gas from the stack of the cement plant was 3400 Nm 3 /h with the CO 2 concentration higher than 15 vol%. The test results showed the CO 2 capture efficiency higher than 85% for 7 hours and the CO 2 concentration of the outlet gas was under 2%. The accumulated time of unit operation test in this pilot plant is more than 600 hours, and that for the fully-continuous looping test is more than 300 hours, respectively. The CO 2 capture rate higher than 1 t/h was obtained, which reached the design point of this pilot plant. It is considered as an important milestone for the future construction of a 30 MWth demonstration plant.

References

7