The Scientific World JOURNAL · 2014 · 31 citations · 43 references
ManagementConstruction ManagementProject ManagementConstruction Project ManagementOptimizationProject SchedulingHydropower EngineeringMulti-objective SchedulingMulti-project SchedulingProject Cost ManagementSchedule OptimizationScheduling OptimizationCost-quality Trade-offFuzzy SetsHydropower SchedulingMakespan OptimizationMulti-project Scheduling Under UncertaintyParticle Swarm OptimizationResource-constrained Multi-project SchedulingResource-constrained Project Scheduling
This paper presents an extension of the multimode resource-constrained project scheduling problem for a large scale construction project where multiple parallel projects and a fuzzy random environment are considered. By taking into account the most typical goals in project management, a cost/weighted makespan/quality trade-off optimization model is constructed. To deal with the uncertainties, a hybrid crisp approach is used to transform the fuzzy random parameters into fuzzy variables that are subsequently defuzzified using an expected value operator with an optimistic-pessimistic index. Then a combinatorial-priority-based hybrid particle swarm optimization algorithm is developed to solve the proposed model, where the combinatorial particle swarm optimization and priority-based particle swarm optimization are designed to assign modes to activities and to schedule activities, respectively. Finally, the results and analysis of a practical example at a large scale hydropower construction project are presented to demonstrate the practicality and efficiency of the proposed model and optimization method.
43
L. A. Zadeh · Information and Control · 1965 · 66.1K citations
James Kennedy, R.C. Eberhart · 2002 · 47.5K citations
A modified particle swarm optimizer
Yibing Shi, R.C. Eberhart · 2002 · 10.2K citations
Scheduling: Theory, Algorithms, and Systems
Michael Pinedo · IIE Transactions · 1996 · 6.3K citations