A Solvable Case of the One-Machine Scheduling Problem with Ready and Due Times
139
Citations
1
References
1978
Year
Mathematical ProgrammingEngineeringTardy JobsComputational ComplexityOne-machine Scheduling ProblemOperations ResearchSolvable CaseSystems EngineeringDiscrete MathematicsParallel ComputingCombinatorial OptimizationJob SchedulerDue TimesScheduling (Computing)Computer SciencePrecedence ConstraintsInteger ProgrammingScheduling AnalysisScheduling ProblemProduction SchedulingScheduling (Production Processes)Ready Time R
We consider a class of n-job one-machine scheduling problems with ready time r(i), processing time p(i), and due time d(i) for each job i. Preemption is not allowed, and precedence constraints among jobs are not assumed. For this problem we show that there is a 0(n 2 )-time algorithm to find a schedule that minimizes the number of tardy jobs, under the assumption that r(i) < r(j) implies d(i) ≤ d(j).