A two-stage heuristic method for balancing mixed-model assembly lines with parallel workstations

Pedro M. Vilarinho, Ana S. Simaria

International Journal of Production Research · 2002 · 171 citations · 22 references

Concepts

TL;DR

The study introduces a new mathematical programming model for mixed‑model assembly line balancing with parallel workstations and zoning constraints, aiming to minimize the number of workstations for a given cycle time while balancing workloads within and between workstations. The authors employ a two‑stage simulated‑annealing procedure that first seeks a sub‑optimal solution to minimize workstations and then refines workloads to balance them across and within parallel workstations. Computational experiments demonstrate that the proposed two‑stage procedure performs very well even on large‑scale problems, as illustrated by a numerical example.

Abstract

This work presents a new mathematical programming model for the mixed-model assembly line balancing problem with parallel workstations and zoning constraints. It allows the user to control the process to create parallel workstations. The model's primary goal is to minimize the number of workstations along the line, for a given cycle time, and its secondary goal is to balance the workloads between and within workstations. A two-stage procedure, using a simulated annealing approach, was developed to tackle this complex problem. The first stage of the procedure looks for a sub-optimal solution to the problem's primary goal, whilst the second stage deals with the secondary goal. The procedure is illustrated with a numerical example and the results from computational experiments show that even for large-scale problems the proposed procedure performs very well.

References

22