A Better Heuristic for Preemptive Parallel Machine Scheduling with Batch Setup Times

Bo Chen

SIAM Journal on Computing · 1993 · 40 citations · 3 references

Concepts

Abstract

This paper addresses the problem of scheduling N jobs on M identical parallel machines with the objective of minimizing the makespan. Jobs are divided into B batches. A sequence-independent batch setup time on a machine is incurred whenever the machine starts its processing on or switches it from a job in one batch to a job in another batch. On the basis of a heuristic for this NP-hard problem proposed by Monma and Potts, a modified heuristic that requires the same implementing time $O(N + (M + B)\log (M + B))$ and is asymptotically optimal is presented. Furthermore, for a certain class of problems, which includes the case in which each batch contains a single job, it has the worst-case performance ratio $\tau _M = \max \{ {\frac{{3M}}{{2M + 1}},\frac{{3M - 4}}{{2M - 2}}} \}$.