Short Shop Schedules

David P. Williamson, L. A. Hall, J.A. Hoogeveen, C.A.J. Hurkens, Jan Karel Lenstra, Sergey Sevast'janov, David B. Shmoys

Operations Research · 1997 · 220 citations · 13 references

DOIFull text

Open access

Concepts

Abstract

We consider the open shop, job shop, and flow shop scheduling problems with integral processing times. We give polynomial-time algorithms to determine if an instance has a schedule of length at most 3, and show that deciding if there is a schedule of length at most 4 is 𝒩𝒫-complete. The latter result implies that, unless 𝒫 = 𝒩𝒫, there does not exist a polynomial-time approximation algorithm for any of these problems that constructs a schedule with length guaranteed to be strictly less than 5/4 times the optimal length. This work constitutes the first nontrivial theoretical evidence that shop scheduling problems are hard to solve even approximately.