Engineering Optimization · 2008 · 43 citations · 16 references
EngineeringIndustrial EngineeringMaintenance EngineeringOptimizationSchedulingCombinatorial OptimizationMaintenance OptimizationMaintenance SchedulingPlant MaintenanceSchedule OptimizationScheduling OptimizationAnt Colony OptimizationHydropower SchedulingLocal SearchMaintenanceMaintenance Of Hydropower PlantsOptimization Of Maintenance SchedulingOptimization-based SchedulingPower Plant Optimization
Abstract It is common practice in the hydropower industry to either shorten the maintenance duration or to postpone maintenance tasks in a hydropower system when there is expected unserved energy based on current water storage levels and forecast storage inflows. It is therefore essential that a maintenance scheduling optimizer can incorporate the options of shortening the maintenance duration and/or deferring maintenance tasks in the search for practical maintenance schedules. In this article, an improved ant colony optimization-power plant maintenance scheduling optimization (ACO-PPMSO) formulation that considers such options in the optimization process is introduced. As a result, both the optimum commencement time and the optimum outage duration are determined for each of the maintenance tasks that need to be scheduled. In addition, a local search strategy is presented in this article to boost the robustness of the algorithm. When tested on a five-station hydropower system problem, the improved formulation is shown to be capable of allowing shortening of maintenance duration in the event of expected demand shortfalls. In addition, the new local search strategy is also shown to have significantly improved the optimization ability of the ACO-PPMSO algorithm.
16
Thomas Stützle, Holger H. Hoos · Future Generation Computer Systems · 2000 · 2.7K citations
Ant colonies for the travelling salesman problem
Marco Dorigo, Luca Maria Gambardella · Biosystems · 1997 · 2K citations
European Journal of Operational Research · 1989 · 1.3K citations