SPE Annual Technical Conference and Exhibition · 2000 · 16 citations · 3 references
EngineeringCivil EngineeringPetroleum EngineeringDrillingReservoir EngineeringWell TestingCasing DesignCementing OperationsFormation TestingHorizontal DrillingWell Test DesignWellbore StabilityCement Slurry DesignCementingCementing DesignCementing TechnologyFracture Zonal IsolationHorizontal Well CementingRemedial CementingZonal Isolation Assessment
Abstract This paper outlines the cement slurry design methodology used to cement one of the world’s longest horizontal well bores. The work detailed has been carried out on ‘M-Site’ of BP Amoco’s Wytch Farm Development on the south coast of Dorset, England, over the past 4–5 years. Of the 17 wells, so far completed on M-Site, none have required remedial cementing work and all reservoir sections exhibit satisfactory zonal isolation, as confirmed by bond log results. The formations to be drilled exhibit very low fracture gradients, with the possibility of losses during the cement job constantly present. The discussion compares and contrasts cementing techniques between vertical and horizontal casings. It looks at procedures and concerns common to both, then describes how downhole temperature calculation and some lab testing techniques, were modified to account for the nature of the horizontal well bore. Output from the computer temperature simulator confirmed assumptions made earlier in the project. Details of the slurry design criteria and testing procedures are discussed. The slurry properties included zero free water and low fluid loss, along with considerable thickening times, to allow for correct placement. The discussion includes hole cleaning measures, and the influences of mechanical contribution, such as centralisers and pipe movement. Spacers and flushes with controlled flow regimes have been used to provide optimum mud and solids removal. In addition, an outline of the computer simulation programme used for well bore analysis is shown to be invaluable to the design engineer, by allowing modification of many inputs very quickly.
3